Thermal Power & Grid Infrastructure Projects in Rajasthan

57 upcoming and ongoing thermal power & grid infrastructure projects in Rajasthan worth ₹118,532 Cr, with investment, location, project stage and latest status. Last updated 06 Mar 2026.

Projects tracked
57
Total investment
₹118,532 Cr
Pre-project / Under construction
0 / 0
Added in the last 30 days
0

Latest thermal power & grid infrastructure projects in Rajasthan

Showing 1–5 of 57
  1. Under Implementation Thermal Power & Grid Infrastructure Projects Updated

    Rs.1459 Million New Electricity Transmission Project in Bikaner, Rajasthan

    Rajasthan From 1000 Million to 4999 Million

    A major utility is executing a ₹1,459.8 million power transmission upgrade in Bikaner, Rajasthan. The project adds two 500 MVA transformers and 220 kV bays at the Bikaner-IV station. Currently in the Notice to Proceed stage via the EPC route, construction began in May 2025 and is scheduled for completion by February 2027.

    View project
  2. Under Implementation Thermal Power & Grid Infrastructure Projects Updated

    Rs.1134 Million New Grid Sub Station Project in Jaisalmer, Rajasthan

    Rajasthan From 1000 Million to 4999 Million

    A new grid substation project is planned in Bhopa, Jaisalmer, Rajasthan, featuring 220/132 kV 1×160 MVA and 132/33 kV 1×50 MVA capacities, with an estimated cost of Rs. 1,134.6 million. Construction is scheduled from July 2025 to March 2027. As of September 2025, the project is at the DPR/feasibility study stage and will be developed through the EPC route.

    View project
  3. Under Implementation Thermal Power & Grid Infrastructure Projects Updated

    Rs.1226 Million New Grid Sub Station Project in Sikar, Rajasthan

    Rajasthan From 1000 Million to 4999 Million

    A new grid substation project is planned in Kanwat, Sikar, Rajasthan, featuring a 220/132 kV 1x160 MVA and a 132/33 kV 1x40/50 MVA unit. With an investment of ₹1,226.2 million, construction will run from April 2025 to December 2026. As of September 2025, it is at the Notice to Proceed stage under EPC execution.

    View project
  4. Under Implementation Thermal Power & Grid Infrastructure Projects Updated

    Rs.1323 Million New Grid Sub Station Project in Bikaner, Rajasthan

    Rajasthan From 1000 Million to 4999 Million

    A new grid substation project is planned in Nokhra, Bikaner, Rajasthan, featuring 220/132 KV 1×160 MVA and 132/33 KV 1×50 MVA capacity. The project, costing Rs. 1,323.4 million, aims to strengthen the regional power transmission network. Construction is scheduled from July 2025 to March 2027 and is currently at the Notice to Proceed stage via the EPC route.

    View project
  5. Under Implementation Thermal Power & Grid Infrastructure Projects Updated

    Rs.1615 Million New GIS Substation Project in Sawai Madhopur, Rajasthan

    Rajasthan From 1000 Million to 4999 Million

    A new GIS substation project is planned in Bhadoti, Sawai Madhopur, Rajasthan, comprising 220/132 kV (1×200 MVA) and 132/33 kV (1×50 MVA) capacities. The project is estimated to cost ₹1,615 million, with construction from August 2025 to June 2027. As of September 2025, the proposal has been submitted to the State Environment Impact Assessment Authority for clearance.

    View project