  1. Project Work Commenced Steel Projects Updated

    Rs.240 Million MS Ingot/Billet Expansion Project in Raigarh, Chhattisgarh

    Chhattisgarh From 100 Million to 999 Million

    A steel company is expanding its MS billet unit in Raigarh, Chhattisgarh, increasing capacities across MS billets, rerolled products, and MS pipes, while maintaining its 20,000 TPA fabrication unit. The 4.632-hectare project, costing ₹240 million, secured state pollution consent in February 2025, with construction planned from November 2026 to July 2027 and environmental clearance under final review.

    View project
  2. Under Implementation Steel Projects Updated

    Rs.1986 Million Hot Leveller No.1 of Plate Mill Replacement Project in Durg, Chhattisgarh

    Chhattisgarh From 1000 Million to 4999 Million

    A project is underway at a steel plant in Durg, Chhattisgarh, involving the replacement of Hot Leveller No.1 of the plate mill. With an estimated investment of ₹1,986.2 million, construction began in August 2024 and is scheduled to conclude by July 2026. As of September 2025, the project has reached the Notice to Proceed stage under the EPC route.

    View project
  3. Under Implementation Steel Projects Updated

    Rs.8841 Million Coke Oven Battery Rebuilding Project in Durg, Chhattisgarh

    Chhattisgarh From 5000 Million to 49999 Million

    A steel company plans to rebuild Coke Oven Batteries No. 7 and 8 at Bhilai Steel Plant, Durg, Chhattisgarh. The project, estimated at ₹8,841 million, commenced in January 2024 and is scheduled to complete by October 2025. As of August 2025, the proposal has been submitted to the State Level Environment Impact Assessment Authority for environmental clearance.

    View project
  4. Project Work Commenced Steel Projects Updated

    Rerolled Products Mfg. Project in Raipur, Chhattisgarh

    Chhattisgarh Less than 100 Million

    A new rerolled products manufacturing project is planned in Sarora, Raipur, Chhattisgarh, with a capacity of 30,000 TPA and an estimated cost of Rs. 43.7 million. Construction is scheduled for April 2024, pending environmental clearance underway as of May 2023.

    View project
  5. Project Work Commenced Steel Projects Updated

    Rolling Mill Expansion Project in Durg, Chhattisgarh

    Chhattisgarh NA

    A rolling mill expansion project in Bhilai, Durg, Chhattisgarh, aims to raise capacity from 30,000 to 57,600 tonnes per year, along with a fabrication capacity of 6,000 MTPA. Consent to establish was granted by state pollution control authorities in April 2019 and reaffirmed as of August 2025, enabling the project to proceed.