New & Upcoming Projects in Power Generation Projects in Uttar Pradesh – Page 9

98 upcoming and ongoing power generation projects in Uttar Pradesh worth ?3.06 lakh crore, with investment, location, project stage and latest status. Last updated 16 Oct 2026.

Projects tracked
98
Total investment
₹3.06 lakh crore
Projects above ₹100 Cr
64
Added in the last 30 days
1

Latest power generation projects in Uttar Pradesh

Showing 41–45 of 98
  1. Under Implementation Renewable Power Projects Updated

    Rs.79492 Million New Kandhaura Pumped Storage Project in Sonbhadra, Uttar Pradesh

    Uttar Pradesh More than 49999 Million

    A new pumped storage project in Uttar Pradesh, India, aims to generate 1680 MW capacity at an estimated cost of Rs. 79492.6 million. Construction begins in June 2024, targeting completion by December 2027. Environmental clearance is pending, indicating a commitment to sustainable energy practices.

    View project
  2. Bidding Stage Thermal Power & Grid Infrastructure Projects Updated

    Rs.3272 Million New Substations and Transmission Line Project n Lalitpur, Uttar Pradesh

    Uttar Pradesh From 1000 Million to 4999 Million

    Uttar Pradesh Power Transmission Corporation plans to construct substations and a transmission line in Birdha, Lalitpur, Uttar Pradesh. The project includes a 220/132/33kV substation (1x160+1x40 MVA) and a 30 km Birdha-Lalitpur 220 kV transmission line. Estimated at Rs. 3272.9 million, bids are invited for the project, with a submission deadline of September 13, 2023, as of August 2023.

    View project
  3. Pre Project Stage Thermal Power & Grid Infrastructure Projects Updated

    Rs.19400 Million New Thermal Power Plant in Kanpur, Uttar Pradesh

    Uttar Pradesh More than 49999 Million

    A new 1,980 MW thermal power plant is being planned near Kanpur, Uttar Pradesh, with three units of 660 MW each. The project's cost is estimated at Rs. 19,400 million. The first phase is expected to begin generating power by the end of this year, as of August 2023.

    View project
  4. Under Implementation Renewable Power Projects Updated

    Rs.26717 Million New Musakhand Pumped Storage Project in Chandauli, Uttar Pradesh

    Uttar Pradesh From 5000 Million to 49999 Million

    A company plans to set up the Musakhand Pumped Storage Project, a hydro power plant with a capacity of 600 MW in Chandauli, Uttar Pradesh. The estimated cost is Rs. 26,717.5 million. Construction is scheduled to begin in January 2025 and conclude by December 2027. As of August 2023, the project has been submitted for environmental clearance to the State Level Environment Impact Assessment Authority.

    View project
  5. Pre Project Stage Thermal Power & Grid Infrastructure Projects Updated

    Rs.180000 Million New 'Obra D' Thermal Power Projects in Sonbhadra, Uttar Pradesh

    Uttar Pradesh More than 49999 Million

    The Government plans to develop two 800 MW thermal power projects in Obra, Sonbhadra. The partnership with a central government-owned power generator aims to secure funding for the projects, with 30% equity provided and the rest sourced from financial institutions. This initiative will bolster the state's power generation capacity and support economic growth in the region. The Uttar Pradesh Government is launching the 'Obra D' thermal power project in Sonbhadra, involving two 800 MW plants on a 500-acre site. A 50:50 partnership with a central government-owned power generator ensures efficient execution, with 30% equity from each party and 70% funding from financial institutions. This collaboration underscores dedication to advanced power infrastructure, leveraging expertise for timely completion. The July 2023 agreement signifies progress toward energy demands and regional development.

    View project