New & Upcoming Projects in Metallurgical Industries Projects in Chhattisgarh – Page 36

424 upcoming and ongoing metallurgical industries projects in Chhattisgarh worth ?3.01 lakh crore, with investment, location, project stage and latest status. Last updated 15 Oct 2026.

Projects tracked
424
Total investment
₹3.01 lakh crore
Projects above ₹100 Cr
155
Added in the last 30 days
10

Latest metallurgical industries projects in Chhattisgarh

Showing 176–180 of 424
  1. Project Work Commenced Non-Ferrous Metals Projects Updated

    New Dolomite Mining Project in Mungeli, Chhattisgarh

    Chhattisgarh NA

    A dolomite mining project is proposed in Mungeli, Chhattisgarh. The project aims to establish a mining capacity of 201,316 metric tons per annum. Consent from state pollution control authorities has been secured for the project as of February 2024.

    View project
  2. Project Work Commenced Steel Projects Updated

    Slag Crushing Expansion Plant in Raigarh, Chhattisgarh

    Chhattisgarh NA

    A steel company in Chhattisgarh is expanding its slag crushing plant in Kerajhar, Raigarh, with a capacity increase from 320,000 TPA to 2,112,000 TPA. The project, costing Rs.4130.5 million, has received consent from state pollution control authorities as of February 2024.

    View project
  3. Project Work Commenced Steel Projects Updated

    New Billets & Ingots Mfg. Project in Raipur, Chhattisgarh

    Chhattisgarh NA

    A new billets & ingots manufacturing project in Sarora, Raipur, Chhattisgarh, approved for 25,000 MTPA billets, 4,990 MTPA re-rolled products, and 59,990 MTPA galvanization. State pollution authorities granted consent in Feb '24, emphasizing environmental compliance.

    View project
  4. Under Implementation Non-Ferrous Metals Projects Updated

    Rs.40913 Million New Screening Cum Beneficiation Plant in Dakshin Bastar Dantewada, Chhattisgarh

    Chhattisgarh From 5000 Million to 49999 Million

    A screening cum beneficiation plant is planned in Chhattisgarh, featuring four lines with a total capacity of 750 tons per hour. The Rs. 40,913.3 million project, submitted for environmental clearance, aims to optimize iron ore processing, adhering to stringent environmental standards. Construction is scheduled from September 2024 to August 2029, contributing to economic growth and responsible mining practices in the region.

    View project