Glass / Ceramics Projects in Odisha – Page 2

10 upcoming and ongoing glass / ceramics projects in Odisha worth ₹1,805 Cr, with investment, location, project stage and latest status. Last updated 26 Jun 2026.

Projects tracked
10
Total investment
₹1,805 Cr
Pre-project / Under construction
0 / 0
Added in the last 30 days
0

Latest glass / ceramics projects in Odisha

Showing 6–10 of 10
  1. Under Implementation Glass / Ceramics Updated

    Rs.671 Million New Refractories Unit in Jajpur, Odisha

    Odisha From 100 Million to 999 Million

    A new refractories manufacturing unit is proposed in Jajpur district, Odisha. The project involves setting up a dedicated facility for producing refractory products with an estimated investment of ₹671.5 million. As of February 2026, the proposal has secured investment approval from the Government of Odisha, marking a key milestone toward project implementation.

    View project
  2. Under Implementation Glass / Ceramics Updated

    Rs.4755 Million New Packaging Container Glass Manufacturing Unit in Khordha, Odisha

    Odisha From 1000 Million to 4999 Million

    A new Packaging Container Glass Manufacturing Unit is planned for Khordha, Odisha. The project, costing Rs. 4755.4 million, involves constructing a 46,198 Sqm facility on a 22-acre plot. Construction is scheduled from January 2026 to December 2028. As of September 2025, the project has been submitted for environmental clearance.

    View project
  3. Project Work Commenced Glass / Ceramics Updated

    Rs.5309 Million New Packaging Container Glass Mfg. Unit in Odisha

    Odisha From 1000 Million to 4999 Million

    A company is planning to establish a new packaging container glass manufacturing unit in Khordha, Odisha, with an annual production capacity of 109,500 metric tons. The project, estimated at Rs. 5309.8 million, aims to meet the growing demand for packaging solutions. As of January 2025, approval has been received from the State Level Single Window Clearance Authority.

    View project
  4. Project Work Commenced Glass / Ceramics Updated

    New Electro Fused Ceramics Mfg. Expansion Project in Sundargarh, Odisha

    Odisha Less than 100 Million

    A project in Bijabahai, Panposh, Biramitrapur, Sundargarh, Odisha, aims to expand Electro Fused Ceramics production from 12,000 MT/Y to 24,000 MT/Y using a 3 MVA Electric Arc Furnace, costing Rs. 10 million. As of June 2024, the project has obtained state pollution control consent, focusing on enhancing ceramic manufacturing capacity sustainably.

    View project
  5. Pre Project Stage Glass / Ceramics Updated

    Rs.3500 Million New Glass Containers Mfg. Unit in Cuttack, Odisha

    Odisha From 1000 Million to 4999 Million

    A Leading Sanitary Ware Brand Products Manufacturing Company is planning to take up new glass containers manufacturing unit in Cuttack, Odisha. The project involves setting up new manufacturing unit for glass containers with capacity 1,30,000 tonnes per annum.

    View project