  1. Under Implementation Ferro Alloys Updated

    Rs.1550 Million Ferro alloy Mfg Expansion Project In Saraikela-kharsawan, Jharkhand

    Jharkhand From 1000 Million to 4999 Million

    A major manufacturing expansion project in Raidih-Palgam, Chandil, Jharkhand, plans to increase production to 120,000 TPA of sponge iron and 30,000 TPA of ferro alloys, along with establishing a 20 MW captive power plant. With an investment of Rs. 1,550 million, construction is set to begin in February 2025 and complete by February 2026, pending environmental clearance.

    View project
  2. Project Work Commenced Ferro Alloys Updated

    Ferro Alloy Mfg. Expansion Project in Bokaro, Jharkhand

    Jharkhand Less than 100 Million

    A metallurgical expansion project in Jharkhand, initially targeting silico manganese and ferro manganese, now focuses solely on Ferro Alloy, increasing capacity to 43,200 TPA with an investment of Rs.95 million. The project received approval from state pollution control authorities in July 2019, reflecting adaptability to market shifts and commitment to sustainability.

    View project
  3. Under Implementation Ferro Alloys Updated

    Rs.720 Million New Greenfield Plant in Jamtara, Jharkhand

    Jharkhand From 100 Million to 999 Million

    A new greenfield plant project in Jamtara, Jharkhand, plans to produce 79,200 TPA of Ferro Alloys with an estimated cost of Rs.720 million. Submitted to MOEFCC in May 2023, awaiting essential details for clearance. Construction begins December 2024 and ends June 2025. Environmental clearance process is ongoing as of April 2024.

    View project
  4. Under Implementation Ferro Alloys Updated

    Ferro Alloys Mfg. Unit Expansion Project in Dhanbad, Jharkhand

    Jharkhand Less than 100 Million

    A ferro alloys manufacturer in Dhanbad, Jharkhand, is set to expand its Low Carbon Ferro Chrome unit from 1440 to 4800 TPA, at an estimated cost of Rs. 45 million. Construction begins in February 2024, ending in May 2024. As of October 2023, the project awaits environmental clearance from the Ministry of Environment, Forest and Climate Change of India.