  1. Under Implementation Ferro Alloys Updated

    Rs.1200 Million New Greenfield Ferro Alloy Plant in Giridih, Jharkhand

    Jharkhand From 1000 Million to 4999 Million

    A developer is launching a ₹120 crore greenfield ferroalloy plant in Giridih, Jharkhand, featuring three 9 MVA furnaces. The facility will produce up to 63,200 TPA of various ferroalloys, including low-carbon variants via a 20-ton AOD unit. Construction is slated for December 202… Read more

    View project
  2. Under Implementation Ferro Alloys Updated

    Rs.5500 Million New Greenfield Plant in Giridih, Jharkhand

    Jharkhand From 5000 Million to 49999 Million

    A new Greenfield industrial plant is planned in Manjhiladih, Giridih, Jharkhand, to produce 123,000 TPA Ferro Alloy, 154,000 TPA Pig Iron, or 31,000 TPA Metallurgical Grade Silicon Metal. The facility will include a 6 MW captive power plant, a 20 TPH jigging plant, and a 240,000… Read more

    View project
  3. Under Implementation Ferro Alloys Updated

    Rs.650 Million New Greenfield Ferro Alloys Plant in Bokaro, Jharkhand

    Jharkhand From 100 Million to 999 Million

    A greenfield ferro alloys plant is planned in Bokaro Industrial Estate, Jharkhand, with a proposed capacity of 40,000 TPA for producing Si-Mn, Fe-Mn, Fe-Si, or a combination. The project, estimated at ₹650 million, is scheduled for construction from May 2026 to February 2027. As… Read more

    View project
  4. Under Implementation Ferro Alloys Updated

    Rs.331 Million Ferro Alloys Plant Expansion Plant in Bokaro, Jharkhand

    Jharkhand From 100 Million to 999 Million

    A ferro alloy plant expansion project is being planned in Jharkhand. The project aims to increase the production capacity from 11,500 TPA to 37,500 TPA, and the estimated cost is Rs.290 million. The company has applied for environmental clearance as of August 2018.