New & Upcoming Projects in Automotive Industries Projects in Karnataka – Page 5

94 upcoming and ongoing automotive industries projects in Karnataka worth ?0.90 lakh crore, with investment, location, project stage and latest status. Last updated 15 Oct 2026.

Projects tracked
94
Total investment
₹0.90 lakh crore
Projects above ₹100 Cr
41
Added in the last 30 days
1

Latest automotive industries projects in Karnataka

Showing 21–25 of 94
  1. Project Work Commenced Auto Components / Ancillaries Updated

    Rs.2050 Million New EPS Liner Mfg. Unit in Belagavi, Karnataka

    Karnataka From 1000 Million to 4999 Million

    A new manufacturing unit for EPS liners is being established in Ullagadi Khanapur, Hukkeri, Belagavi, Karnataka, with an estimated investment of Rs. 2050 million. The project received approval from the state Land Allotment Committee in February 2024. As of October 2024, construction has commenced, aimed at enhancing production capabilities to meet growing market demand for EPS products.

    View project
  2. Project Work Commenced Electric Vehicles & Battery Manufacturing Updated

    Rs.2500 Million New Lithium-ion Batteries Mfg. Project in Bellary district, Karnataka

    Karnataka Less than 100 Million

    A new facility focused on chemical and electrical products is being established in the Kudithini industrial area, Bellary district, Karnataka, covering 50 acres. The project, estimated at Rs. 54 million, will produce Lithium Iron Phosphate, Cathode Active Material, and Lithium-ion batteries. Approved by the state Land Allotment Committee in February 2024, construction work has begun as of October 2024.

    View project
  3. Under Implementation Electric Vehicles & Battery Manufacturing Updated

    Rs.15500 Million New Battery Anode Material Mfg. Plant in Ballari, Karnataka

    Karnataka From 5000 Million to 49999 Million

    A new battery anode material manufacturing plant is planned in Haraginadoni, Ballari, Karnataka, with a production capacity of 514,398 TPA and an estimated cost of Rs. 15,500 million. Construction is expected to begin in July 2025 and finish by July 2026. As of September 2024, the project is awaiting environmental clearance from the State Level Environment Impact Assessment Authority (SEIAA).

    View project
  4. Pre Project Stage Electric Vehicles & Battery Manufacturing Updated

    Rs.90000 Million New Anode Plant in Karnataka

    Karnataka More than 49999 Million

    A new anode plant is planned in Karnataka with a total investment of Rs. 90,000 million and an annual production capacity of 90,000 tonnes. The first phase will see Rs. 40,000 million invested to build a 30,000-tonne facility by Q4 2026, with scaling expected by 2031. Groundbreaking is anticipated within six to eight months as of September 2024.

    View project
  5. Pre Project Stage Auto Components / Ancillaries Updated

    Rs.21000 Million Automotive Components Mfg. Expansion Project in Bangalore, Karnataka

    Karnataka From 5000 Million to 49999 Million

    A significant expansion of an automotive components manufacturing facility is planned in Harohalli, Karnataka, with an estimated cost of Rs. 21,000 million. The project will increase production capacity and incorporate advanced technology for better efficiency. As of July 2024, a Memorandum of Understanding (MoU) with the state government has been signed, promising job creation and economic growth.

    View project