  1. Under Implementation Water Supply & Irrigation Projects Updated

    Rs.7667.6 Million Amanat Barrage Project in Palamu, Jharkhand

    Jharkhand From 5000 Million to 49999 Million

    The State Government is planning to take up Amanat barrage project in Palamu, Jharkhand. The project involves construction of a barrage to impound available discharge of the river in the reservoir created.

    View project
  2. Under Implementation Water Supply & Irrigation Projects Updated

    Rs.550 Million Waste Water Sewerage and Sanitation Development in Ranchi, Jharkhand

    Jharkhand From 100 Million to 999 Million

    The Government plans a wastewater sewerage and sanitation development project in Ranchi, Jharkhand. It includes setting up a sewerage line at an estimated cost of Rs. 550.6 million. The project is in the development stage, with the tender awarded, providing an opportunity for contractors.

    View project
  3. Pre Project Stage Water Supply & Irrigation Projects Updated

    Rs.161 Million Tardiha Barrage Project in Godda, Jharkhand

    Jharkhand From 100 Million to 999 Million

    The Government of Jharkhand plans to construct the Tardiha barrage in Godda. With an estimated cost of Rs.161 million, the project aims to address water resource challenges. Currently under development, the project is being implemented by an in-house team, with a detailed project report study in progress.

    View project
  4. Under Implementation Water Supply & Irrigation Projects Updated

    Rs.1106 Million New Rural Water Supply Scheme in Jharkhand

    Jharkhand From 1000 Million to 4999 Million

    The Government of Jharkhand plans to implement a New Rural Water Supply Scheme involving construction of various infrastructure components. These include an intake well, treatment plant, reservoirs, pump house, and distribution network. The estimated project cost is Rs.1106 million, and environmental clearance is being sought as of April 2021.

    View project
  5. Project Work Commenced Water Supply & Irrigation Projects Updated

    Rs.5630 Million Son River Irrigation Project in Palamu, Jharkhand

    Jharkhand From 5000 Million to 49999 Million

    The Government of Jharkhand plans to construct an 82.5km dam on the Son river for irrigation in Palamu. The Rs. 5630 million project is in the development stage, with Sigma R. D. Consultants as the project management consultant, following the EPC route.