Showing 6–10 of 125
  1. Under Implementation Specialty Chemicals Updated

    Specialty Chemicals Expansion Project in Valsad, Gujarat

    Gujarat Less than 100 Million

    A chemicals producer plans a major expansion at its Sarigam facility in Gujarat, increasing specialty chemical and pesticide capacity from about 2,039 MT/month to 18,234 MT/month. The Rs.99.6-million project received initial clearance in May 2020 and final approval in July 2020. As of November 2025, it involves large-scale capacity growth to over 205,500 TPA and development of adjoining land.

    View project
  2. Under Implementation Specialty Chemicals Updated

    Rs.2365 Million Hydrofluorocarbon Expansion Project in Surat, Gujarat

    Gujarat From 1000 Million to 4999 Million

    A specialty chemicals manufacturer is executing a multi-phase expansion at its Surat, Gujarat facility. The project includes increasing organic and inorganic product capacities and adding new HFC production of up to 15,000 MTPA, raising total output significantly. With cumulative investments exceeding Rs.8,465 million, construction is ongoing, and the new capacity is expected by Q3 FY27, pending environmental clearance.

    View project
  3. Pre Project Stage Specialty Chemicals Updated

    Rs.750 Million New Multi Purpose Plant Debottlenecking Project in Dahej, Gujarat

    Gujarat From 100 Million to 999 Million

    A chemical manufacturer is developing a new multi-purpose plant at Dahej, Gujarat, with an estimated investment of Rs.1,950 million. The project, executed by its wholly owned subsidiary, will be funded through internal accruals and debt. As of November 2025, debottlenecking work is underway to enable production of a fluoro-intermediate for agrochemicals, scheduled for completion by Q3 FY27.

    View project
  4. Under Implementation Specialty Chemicals Updated

    Rs.170660 Million Carbon Black Manufacturing Expansion Project in Kachchh, Gujarat

    Gujarat More than 49999 Million

    A new Carbon black Manufacturing facility is planned in Gujarat's Village Paddhar. With an estimated cost of Rs. 1200 million, the facility aims for 11500 TPM capacity. Environmental clearance efforts started in March 2017, continuing with a modern plant plan in March 2019. Subsequent expansions, like a 20 MW Turbine and tire manufacturing, added Rs. 250 million investment. The project's scope expanded in November 2020, targeting a 4 LTPA carbon black facility, 90 MW CPP, and tire manufacturing, all pending environment clearance. As of May 2023, carbon black capacity expansion to 192600 TPA with Rs. 13690 million investment awaits approval. Essential project details are submitted to India's Ministry of Environment, Forest, and Climate Change for clearance consideration.

    View project
  5. Under Implementation Specialty Chemicals Updated

    Rs.3700 Million Rubber Chemicals Mfg. Expansion Project in Dahej, Gujarat

    Gujarat From 1000 Million to 4999 Million

    An expansion project at Dahej and Navi Mumbai facilities aims to boost rubber chemicals and intermediates capacity from 11,990 MT/month to 21,790 MT/month, along with a 100 MT/month formulation unit. The revised investment stands at ₹3,700 million. Construction is scheduled between October 2025 and April 2026, with the proposal currently under review by the State Level Environment Impact Assessment Authority (SEIAA).

    View project