New & Upcoming Projects in Manufacturing Projects in Gujarat – Page 5

212 upcoming and ongoing manufacturing projects in Gujarat worth ?3.99 lakh crore, with investment, location, project stage and latest status. Last updated 04 Sep 2026.

Projects tracked
212
Total investment
₹3.99 lakh crore
Projects above ₹100 Cr
67
Added in the last 30 days
0

Latest manufacturing projects in Gujarat

Showing 21–25 of 212
  1. Under Implementation Electronics, Semiconductors & Data Centers Updated

    Rs.10470 Million New Electrical Cables and Wires Mfg. Unit in Ahmadabad, Gujarat

    Gujarat From 5000 Million to 49999 Million

    A new electrical cables and wires manufacturing unit is planned in Memar, Bavla taluka, Ahmedabad, Gujarat. The project includes construction of an industrial shed for production, with an estimated investment of Rs. 10,470 million. Construction is scheduled from February 2026 to March 2028, and the project proposal has been submitted to the State Environment Impact Assessment Authority for clearance.

    View project
  2. Under Implementation Other Manufacturing Updated

    Rs.7425 Million New Plaster Bord and Ceiling Tile Mfg. Plant in Bharuch, Gujarat

    Gujarat From 5000 Million to 49999 Million

    A new plaster board and ceiling tile manufacturing plant is planned at Pakhajan, Vagra, Bharuch district, Gujarat. The project includes production of 2,583,333 Sq. M/month of plaster board and 500,000 Sq. M/month of ceiling tiles, with an estimated investment of Rs. 7,425.8 million. Construction is scheduled from April 2026 to May 2027, and environmental clearance has been submitted.

    View project
  3. Under Implementation Other Manufacturing Updated

    Rs.5748 Million Synthetic Organic Chemicals Mfg, Unit Expansion Project in Gujarat

    Gujarat From 5000 Million to 49999 Million

    A Gujarat-based firm plans to expand its Synthetic Organic Chemicals (Resin Products) manufacturing unit from 60,000 MT/annum to 90,000 MT/annum at an estimated cost of ₹5,748 million. Construction is scheduled from May to November 2026. The project, located in Sherpura, Savli, Vadodara, has been submitted to the State Environment Authority for clearance as of January 2026.

    View project
  4. Under Implementation Electronics, Semiconductors & Data Centers Updated

    Rs.132254 Million Semiconductor Assembly and Test Facility Expansion Project in Ahmedabad, Gujarat

    Gujarat More than 49999 Million

    A semiconductor assembly and test facility in Sanand, Gujarat, is planned for expansion (Phases 2 & 3) covering assembly, testing, marking, and packaging (ATMP). The project, estimated at Rs. 132,254 million, will begin construction in October 2025 and complete by December 2028. Environmental clearance has been submitted to the State Level Authority as of January 2026.

    View project
  5. Under Implementation Other Manufacturing Updated

    Silica Sand Washing Project in Bharuch, Gujarat

    Gujarat Less than 100 Million

    A minerals company plans to develop a silica sand washing project in Rajpardi, Bharuch, Gujarat, with an estimated cost of Rs.19.8 million. Construction is scheduled from June to August 2026, and as of December 2025, the project has been submitted for environmental clearance.

    View project