Projects in Haryana – Page 34

719 upcoming and ongoing projects in Haryana worth ₹417,810 Cr, with investment, location, project stage and latest status. Last updated 08 Oct 2026.

Projects tracked
719
Total investment
₹417,810 Cr
Pre-project / Under construction
0 / 0
Added in the last 30 days
8

Latest projects in Haryana

Showing 166–170 of 719
  1. Under Implementation Distillery / Ethanol Updated

    Rs.300 Million Grain based Ethanol Plant Expansion Project in Panchkula, Haryana

    Haryana From 100 Million to 999 Million

    A grain-based ethanol plant in Firozpur, Panchkula, Haryana, is expanding from 215 KLPD to 300 KLPD and adding a 6.0 MW cogeneration power plant. The Rs. 300 million project will start in September 2024 and finish by March 2025. Environmental clearance is under review by the Ministry of Environment, Forest, and Climate Change as of June 2024.

    View project
  2. Under Implementation Hospitals / Healthcare Updated

    Rs.18120 Million Super Speciality Hospital Expansion Project in Faridabad, Haryana

    Haryana From 5000 Million to 49999 Million

    An expansion project for a super specialty hospital in Badshapur, Palwali, Faridabad, Haryana, involves adding one additional block with a built-up area of 3593.82 sqm. Estimated at Rs. 18120 million, construction began in October 2016, slated for completion by May 2029. As of June 2024, the project awaits environmental clearance from the State Level Environment Impact Assessment Authority, emphasizing adherence to regulatory standards for sustainable healthcare infrastructure expansion.

    View project
  3. Under Implementation Hospitals / Healthcare Updated

    Rs.6250 Million Hospital Expansion Project in Faridabad, Haryana

    Haryana From 5000 Million to 49999 Million

    A hospital expansion project at ESIC Medical College And Hospital in Faridabad aims to add 500 beds, increasing capacity from 650 to 1150 beds. The estimated cost is Rs. 6250 million. Construction begins in August 2024, targeting completion by March 2028. Currently in the Detailed Project Report and Feasibility Study phase, the project employs the Engineering, Procurement, and Construction (EPC) approach.

    View project
  4. Project Work Commenced Other Chemicals Updated

    Rs.135 Million New Lubricating Oils Mfg. Project in Gurgaon, Haryana

    Haryana From 100 Million to 999 Million

    A new manufacturing project in Sector-37, Pace City-II, Gurgaon, Haryana, will produce lubricating oils, grease, and petroleum-based products. The project is estimated to cost Rs. 135.792 million and has received consent from the state pollution control authorities to proceed as of May 2024.

    View project
  5. Project Work Commenced Other Chemicals Updated

    New Synthetic Detergents And Soaps Mfg. Project in Jhajjar, Haryana

    Haryana Less than 100 Million

    A new synthetic detergents and soaps manufacturing project, estimated at Rs.83.5 million, is planned in HSIIDC Bahadurgarh, Haryana. Excluding formulation, the project has received consent from state pollution control authorities as of May 2024.