Adani Energy Solutions announced that it has completed construction of the largest interregional 765 KV Warora-Kurnool energy transmission line.
According to a statement, the project, which spans 1,756 circuit kilometres (ckm) across Maharashtra, Telangana, and Andhra Pradesh, will enhance the national grid to provide a seamless power flow of 4,500 MW between western and southern regions.
Adani Energy Solutions Ltd (AESL) completed the commissioning of the Warora Kurnool Transmission Ltd (WKTL), according to the announcement.
WKTL was incorporated in April 2015 to establish an additional inter-regional alternate current link for import into the southern region, i.e., Warora-Warangal and Chilakaluripeta-Hyderabad-Kurnool, along with the creation of a 765/400 kV sub-station in Warangal.
Company : Adani Energy SolutionsWarora Kurnool Transmission
Recent News
◉ SWELECT Energy secures over 150 MW of solar module - Mar 13,2025◉ RVNL emerges as lowest bidder for Rs 554.64 crore road contract - Mar 13,2025
◉ MoU inked for developing Multi-Modal Logistics Park in Varanasi - Mar 13,2025
◉ Danfoss India to invest Rs 1,200 crore by 2028 - Mar 13,2025
◉ SJVN to develop Rs 9,500 crore pumped storage project - Mar 13,2025
◉ JNPA signs concession agreement for Rs 285-crore agri-processing facility - Mar 13,2025
◉ Montra Electric opens e-SCV manufacturing plant in Chennai - Mar 13,2025