Rooppur NPP Power Unit I gets steam generators

At power unit No. 1 of the Rooppur NPP being built in the People’s Republic of Bangladesh, all four steam generators have been put in the planned position (by Rosatom Engineering Division ASE JSC which is the general contractor for the NPP construction).

Specialists from the Energospecmontazh JSC subcontracting organisation completed assembly operations to place the steam generators in their proper positions in the reactor compartment of the power unit according to the agreed schedule.

 