Urban Extension Road Project to be completed by mid-September

The Urban Extension Road Project (UER-II) in Delhi’s first phase of construction, or packages 1, 2, and 3, is on schedule to be finished by September, well ahead of the original target date of October 2023.

According to senior officials from the Indian Ministry of Road Transport and Highways, “construction of the first phase of the UER-II, with a length of 38.111 km, is on schedule to be inaugurated by mid-September.”

According to a senior official of the National Highways Authority of India (NHAI), the UER-construction II’s is currently about 60% complete, and the pace of work has greatly increased recently.

“So far, 60 percent of the work is complete: 55 percent on Package 1, 45 percent on Package 2, 90 percent on Package 3, 72 percent on Package 4, and 67 percent on Package 5 have been completed,” the official said.

 

Site Moved. Visit our New Website

We have moved this news site from this URL to https://www.newprojectstracker.com/capex-news .

Visit this site for regular updates

Buy Latest Research Reports

Jayaparakash Sampath

Founder & CEO at NPT Research Information Services

Related Posts