Triveni Engineering & Industries Ltd‘s board of directors announced that the current distillery at Sabitgarh, District Bulandshahr, Uttar Pradesh, has been expanded and is now functioning at 200 KLPD. With this, the Company’s overall distillation capacity has grown to 520 KLPD.
The augmentation of distillation capacity from 520 to 660 KLPD is on schedule and should be finished by July of 2022.
The board approved the modernization of three of the existing sugar units at Khatauli, Deoband and Sabitgarh, all in the State of Uttar Pradesh at a total cost of about Rs.130 crore, which shall be completed by October’2022 and approved the expansion of power transmission business at a total cost of about Rs.80 crore, which shall be completed by March’2023.