By mid-2022, ongoing civil works for the restoration of historical Indore buildings such as Rajwada Palace, Gopal Mandir, and Malhar Rao Holkar Chhatri, as well as the construction of Khajrana Ganesh Mandir’s gate, Marathi Kala Sankul, Jawahar Marg Bridge to Chandrabhaga Road, redevelopment of Nehru Park, and road widening/construction between Bada Ganapati Square and Krishnapura Chhatri, should
Indore Smart City Development Limited is in charge of the aforementioned projects.
In a meeting of the District Development Coordination and Monitoring Committee presided over by MP Shankar Lalwani, ISCDL CEO Rishabh Gupta revealed the expected completion date for ongoing civil work of Gopal Mandir on March 31, Rajwada Place and Jawahar Marg Bridge to Chandrabhaga Road on July 31, Khajrana Ganesh Mandir’s gate on April 15, Malhar Rao Holkar Chhatri and Nehru Park on May 31, Marathi Kala Sankul on August 31, road widening/construction between Bada Ganapati Square and Krishnapura Chhatri by end of June, this year.