Candour Techtex gives updates on technical textiles projects

For our new Technical textiles project, a building covering roughly 55,000 square feet is currently being constructed on industrial property at Plot No. C-6, Malegaon Textile Park (Ajang-Ravalgaon Industrial Area), which covers approximately 22,681 square metres (or 5.5 acres). The structure was built to accommodate the installation of four lines of coating and flocking equipment, the company said.

The Coating machine, Flocking machine, Laboratory coating machine & Lamination machine for the 1st Line imported from UK have already arrived at the site and the installation is in progress. The machines are expected to be installed by end of January, 2023.

The Foam mixer machine for the 15 line imported from Germany is already shipped and is expected to land in India by mid January, 2023 and installed by end of January, 2023.

Site Moved. Visit our New Website

We have moved this news site from this URL to https://www.newprojectstracker.com/capex-news .

Visit this site for regular updates

Buy Latest Research Reports

Jayaparakash Sampath

Founder & CEO at NPT Research Information Services

Related Posts