Bhansali Board discusses capacity expansion projects

The capacity expansion projects were discussed by the Board of Directors of Bhansali Engineering Polymers Limited during a meeting.

The Board of Directors noted that the Company’s efforts to improve operational efficiencies and process improvements at both plants have resulted in an increase in overall ABS production from 65,000 TPA to 75,000 TPA (10,000 TPA additional ABS production) without incurring any Capex, effective April 1, 2022.

The Company has already secured the necessary legislative clearances (such as Environmental Clearance, Consent to Establish, Consent to Operate, and so on) from various government agencies for the aforementioned capacity expansion

 