‘Development of 6 lane Access Controlled Greenfield highway from KM 162.500 to KM 203.100, Baswantpur to Singondi Section of NH 150 C (Package 4 of Akkalkot KNT of TS Border) on Hybrid Annuity Mode (HAM) under Bharatmala Pariyojana’ was the project that Ashoka Buildcon Limited submitted to the National Highways Authority of India.
At the Financial Bid opening meeting in New Delhi on March 29, 2022, the Company was named “the Lowest Bidder.” The project’s estimated bid project cost is Rs.1,079 crore.
From the scheduled date, the construction time is 912 days.